Symptom
The screen layout for the work centre Resource Scheduler cannot be modified currently.
Reproducing the Issue
- Go to the work centre Resource Scheduler.
- Go to the view Resource Scheduler.
- Click on Week.
- Enter Adaptation Mode > Edit Master Layout.
- Attempt to change the layout by size etc.
RESULT: changes cannot be made.
Cause
The work centre Resource Scheduler is using a Gantt chart. This is currently not open to any change or modification.
Resolution
This is current expected system behaviour.
Keywords
KBA , AP-LEC , Logistics Execution Control , How To
Product
SAP Cloud for Customer core applications 1708 ; SAP Cloud for Customer core applications 1711 ; SAP Hybris Cloud for Customer add-ins 1708 ; SAP Hybris Cloud for Customer add-ins 1711