Symptom

Change Immediately option is not available for Activities in your Project under Overview view in Business Configuration workcenter.

Environment

  • SAP Business ByDesign
  • SAP Cloud for Customer

Reproducing the Issue

  1. Go to Business Configuration workcenter.
  2. Go to Overview view.
  3. Select Open Activity List.
  4. Select any activity e.g. Quantities and Units of Measure.

Cause

In the given scenario the reported tenant is a Test System and it is connected to Productive System and there is already a change project copied from Productive system and this change project is the main workspace.

Resolution

If you want to perform any changes to a fine tuning activity, then activity should be added to the change project and then you can perform the changes.
Note: Saved changes will be visible only in the Test system until you trigger merge. After merge, changes will reflect in production system.

See Also

Keywords

 Change Immediately, Business Configuration, Activity, C4C, BYD , KBA , SRD-MD-OM , Organizational Management , How To

Product

SAP Business ByDesign all versions ; SAP Hybris Cloud for Customer add-ins 1605 ; SAP Hybris Cloud for Customer add-ins 1608 ; SAP Hybris Cloud for Customer add-ins 1611 ; SAP Hybris Cloud for Customer add-ins 1702 ; SAP Hybris Cloud for Customer add-ins 1705 ; SAP Hybris Cloud for Customer add-ins 1708 ; SAP Hybris Cloud for Customer add-ins 1711