Symptom
After the creation of a subcontracting PO with Bill of material, the BOM is not exploding in PO as expected. Below settings are in place:
- The material has the procurement type defined as External procurement
- Material BOM is customized (T-code: CS01) correctly
- Validity dates are in range as SAP Notes 196684 and 13023
Read more...
Environment
- Material Management
- SAP S/4HANA All versions
Product
SAP S/4HANA all versions
Keywords
ME154, BOM, BOM explosion, BOM usage, production version, Bill of Material, OS31, subcontracting, MKAL, OPPQ, ME 154, VERID, S/4 HANA, MARC-ALTSL, ECC , KBA , ok , MM-PUR-GF-SC , Subcontracting , MM-PUR-PO , Purchase Orders , PP-MRP , Material Requirements Planning , LO-MD-BOM , Bills of Material , How To