2337154 - Merge of Change Project Occurs in Test System Although the Activity Says "Merge changes with production system"

Symptom

You are using a test system and performed a merge of a change project through the activity Merge changes with production system.

Nevertheless the changes have been implemented in test instead in production system. 

Reproducing the Issue

  1. Go to Business Configuration and Select Implementation Projects view
  2. Open the activity list
  3. Go to Go-Live tab
  4. Merge activity says Merge Changes

Cause

This Test system was requested as full copy of production your system (Copy of Source System). Therefore, the system behaves like a production and the merge occurs locally instead in your production system itself.
For further information, please check the document "2136036 - How to Request a New System".

Resolution

System is working as expected.

Keywords

KBA , merge of change project , merge changes , AP-RC-BCT , Business Config. Tools (SAP Business ByDesign , How To

Product

SAP Business ByDesign all versions