Symptom

When copying a project with referencing another, the settlement rule of old WBS will be assigned to new WBS, and will not be updated although you changed settlement rule and release for new project definition.


Read more...

Environment

  • SAP ERP Project System (PS)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP Enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA, on-premise

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

settlement rule, copy, user status profile , KBA , PS-COS-PER , Automatic and Periodic Allocations , PS-ST-WBS , Work Breakdown Structure , Problem