Symptom
A Work Package Completed indicator can be set for project time recording.
Reproducing the Issue
- Go to Project Team work center.
- Select the view Edit Time Sheet.
- Select the project task and the day.
- Input the hours and enter here you will see the Work Package Completed Indicator.
Cause
When the Work Package Completed indicator can be set for project time recording in the employee time sheet this information is passed to project management, you can see this information in the display time confirmation of project plan work.
Resolution
- Go to the Project Management work center.
- Select and edit the project.
- Select the task
- Navigate to the Work tab
- Select the Employee (for which the Work Package Completed indicator is set)
- Select the Display Time confirmation Button here you can see the Completed button is enabled if the Work Package Completed indicator is set in the Time Sheet.
Keywords
KBA , work package , project team , SRD-HR-TLM , Time and Labour Management , How To
Product
SAP Business ByDesign all versions