SAP Knowledge Base Article - Public

2401304 - Scheduled Offering error message when editing a segement

Symptom

Error mesage appears when trying to edit schedule offering segment

s55.png

Environment

SuccessFactors Learning Management System (LMS) - All Supported Versions

Reproducing the Issue

1. Create two schedule offerings that start on the same date (i.e 15/12/2106) but with different starting and end times and enroll two users in both

  • SO1 (schedule offering 1) starts on 15/12/2106 and runs from 09:00 am-05:00pm
  • SO2 (schedule offering 2) starts on 15/12/2106 and runs from 07:00 pm-09:00pm

S1.png

 

2. The users learning plan will be updated showing that they are enrolled and on what date the course starts

s22.png

3. Clicking on the course will provide more details on the starting and finishing times

S2.png

4. Admin enrolled the same users in the second schedule offering that commenses on the same date (15/12/2016) but with different starting time (07:00pm-09:00pm)

s33.png

 

5. Later it's decided that admins want to change the starting time of schedule offering two for example (Maslany-China-Test) from 07:00pm to 11:00am instead ( Please note that users are already enrolled in the first schedule offering that starts at 09:00am)

s44.png

6. An error message will appear as a reason of time clash between the two schedule offerings

s55.png

Resolution

This is an expected behaviour.

When LMS detects any conflict between two schedule offerings an error message will appear.

Keywords

Scheduled Offering error; Scheduled Offering conflict; segment; scheduled conflict; , KBA , LOD-SF-LMS-COR , LMS Core - Items, Catalog, Curricula , LOD-SF-LMS , Learning Management System , Problem

Product

SAP SuccessFactors Learning all versions