SAP Knowledge Base Article - Public

2406599 - System Displays the Error "Internal Error" while Creating a Depreciation Run

Symptom

You have created a Depreciation Run, however on the Messages tab you see the error: Internal Error

Reproducing the Issue

  1. Go to Fixed Assets work center.
  2. Go to Periodic TasksDepreciation.
  3. Click on New button and then choose Fixed Asset Depreciation Run.
  4. Complete the Run for correspondent Period/Year and execute it.
  5. Go back to Periodic Tasks > Depreciation.
  6. Search and open the newly created Depreciation Run XYZ.
  7. Go to Erroneous Fixed Assets tab.
  8. You will see some assets with the error: Internal Error

Cause

Error is happens because a Balance Carryforward has been executed for Step 1

Resolution

In order to resolve the issue you need to reverse the Balance Carryforward Run created for the respective Period/Year, as per following steps:

  1. Go to General Ledger Work Center.
  2. Go to Periodic Tasks > Balance Carryforward.
  3. Select the respective Balance Carryforward Run with Step 1 executed for the company.
  4. Click Reverse button.

Once the Balance Carryforward is reversed, you are able to execute the Depreciation Run.

Keywords

KBA , SRD-FIN-FA , Fixed Assets , How To

Product

SAP Business ByDesign all versions