Symptom
If the utilization rate of a resource or its shift definition is changed, an automatic rescheduling of PP/DS planned orders takes place on the resource. However, the Goods Receipt (GR) activities of these orders keep their original dates/times and are not moved with the rescheduled production activities.
Read more...
Environment
- SAP Supply Chain Management (SCM)
-
SAP Advanced Planning and Optimization (SCM-APO)
-
SAP enhancement package for SAP Supply Chain Management
-
SAP Supply Chain Management Production Planning and Detailed Scheduling (SCM-APO-PPS)
-
SAP ERP, add-on for embedded Production Planning and Detailed Scheduling (SCM-APO-PPS-ERP)
-
SAP S/4HANA 1610
-
SAP enhancement package 8 for SAP ERP 6.0
Product
Keywords
Resourcenauslastung, Ressourcenkapazität, Verschiebung von Aktivitäten, Nichtarbeitszeiten, non-working times, breaks, days off, downtime, capacity requirement, LiveCache, SCM-APO-PPS-SCF, SCM-APO-MD-RE , KBA , SCM-APO-PPS-SCF , Scheduling Functions , SCM-APO-MD-RE , Resource , Problem