Symptom
In the product view, you convert a planned order to a production order and, in a later point, reschedule this production order to a different date. The basis start and end dates which can be seen in ECC are not changed. However, you notice that the scheduled start and end dates does change.
This might lead to planning inconsistencies like for instance, if you perform a ATP check on these orders.
Read more...
Environment
- SAP ERP Central Components
- SAP Supply Chain Management (SCM), Advanced Planning and Optimization (APO)
Product
Keywords
planned, order, production, basic, dates, start, end, scheduled, basic dates, scheduled dates , KBA , SCM-APO-INT-PPS , PP-DS / Production and Process Order , Problem