Symptom
When running Project Systems (PS) reports, costs (planned/actual) from deleted network activities are displayed on WBS level.
Read more...
Environment
- SAP ERP Project System (PS)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
KPOR_DEL_ORDER_CORRECT, planned, S_ALR*, DLFL, rolled-up, COSP, COSS, Network, CJ20N, RPSCO, cost element, hierarchy, actual cost, S_ALR_87013570, COSSP, CJEN, OLC, LOG_EAM_OLC, LOG_EAM_OLC2, OPJB , KBA , s_alr_8701354 , cns41 , cn41 , PS-COS-PLN-PLN , Planned Costs , PS-IS , Information System , PS-COS-ACT , Actual Costs and Forecast , How To
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.