2425545 - Actual dates for project tasks overwrite planned dates

Symptom

You maintain actual dates for a Project Management task (e.g. manually by carrying out a confirmation for the task, or automatically by completing a task).

The new actual dates overwrite the previous planned/scheduled dates for the task, i.e. the actual dates become the new planned dates.


Read more...

Environment

SAP Portfolio and Project Management (PPM)

Product

SAP Portfolio and Project Management all versions

Keywords

planned VS actual, actual start, actual finish, planned start, scheduled start, earliest start, latest start, start constraint, planned finish, scheduled finish, earliest finish, latest finish, finish constraint, milestone, task, phase, project, schedule, scheduling, confirm, confirmation, change , KBA , PPM-PRO , Project Management , How To