Symptom
You maintain actual dates for a Project Management task (e.g. manually by carrying out a confirmation for the task, or automatically by completing a task).
The new actual dates overwrite the previous planned/scheduled dates for the task, i.e. the actual dates become the new planned dates.
Read more...
Environment
SAP Portfolio and Project Management (PPM)
Product
Keywords
planned VS actual, actual start, actual finish, planned start, scheduled start, earliest start, latest start, start constraint, planned finish, scheduled finish, earliest finish, latest finish, finish constraint, milestone, task, phase, project, schedule, scheduling, confirm, confirmation, change , KBA , PPM-PRO , Project Management , How To