2434110 - Actual finish date of summary task before completion of all subtasks

Symptom

In a project with summary tasks, one of the subtasks under a summary task is completed.

The Actual Finish date of the summary task is populated with today's date, even though other subtasks below this summary task are not yet completed.


Read more...