Symptom
From Stock checkbox is not enabled in material of a project task hence unable to flag From Stock material.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Project management work center.
- Select Projects view.
- Select Project XYZ and Edit-> Project Plan (XYZ stands for Project ID).
- Navigate to relevant project task.
- Go to Material tab here you can see From Stock checkbox is grayed out for some material.
Cause
Once the material actual quantity is updated the From Stock checkbox is not enabled and the system will not allowed to change the material process type.
It means that you have already consumed the material as Non stock in the project hence the From Stock option is grayed out.
Resolution
System works as expected.
Keywords
From Stock, Project, Project Task, Material , KBA , SRD-PRO-PMN , Project Management , How To
Product
SAP Business ByDesign all versions