2461220 - No plan cost calculated for network activity

Symptom

You create a material component under a network activity, it generates a purchase requisition and a reservation for the WBS-element, but when you check the plan cost for the network, network activity, WBS-element, no plan cost is updated/calculated at all.


Read more...

Environment

  • SAP ERP Project System (PS)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP Enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA, on-premise

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

planned cost, cost planning, project information report, costing report, cost element report , KBA , PS-COS-PLN , Costs , How To