2469491 - Source of Supply selection during heuristic run

Symptom

  • After running the Product Heuristic in PP/DS, new orders are created with a different Source of Supply than expected.
  • The orders are generated with a Source of Supply that has lower Procurement Priority

  • The planning logs display the following messages:

-Error/delay with source XXXXX for product XXXXX; try source XXXXX;
-Order XXXXX with source XXXXX created on time on 13.03.2015 12:00:00; desired date 13.03.2015 12:00:00


Read more...

Environment

Supply Chain Management (SCM)

Product

SAP S/4HANA all versions ; SAP Supply Chain Management all versions ; SAP enhancement package for SAP Supply Chain Management all versions

Keywords

PDS, PPM, procurement, priority, alternative, resource assignment, work center, workcenter, WC, resource, source of supply, , KBA , /sapapo/rrp313 , /sapapo/rrp319 , procurement priority flag , flag , low priority , SCM-APO-MD-SRC , Sources of Supply , SCM-APO-PPS , Production Planning and Detailed Scheduling , Problem