SAP Knowledge Base Article - Preview

2469491 - Source of Supply selection during heuristic run

Symptom

  • After PP/DS heuristic ran you see that new orders have a Source of Supply different from what you expect
    Or
  • The orders are being generated with a source of supply of lower procurement priority

  • In the planning logs you see messages like:

Error/delay with source XXXXX for product XXXXX; try source XXXXX;
or
Order XXXXX with source XXXXX created on time on 13.03.2015 12:00:00; desired date 13.03.2015 12:00:00


Read more...

Environment

Supply Chain Management (SCM)

Product

SAP Supply Chain Management all versions

Keywords

PDS, PPM, procurement, priority, alternative, resource assignment, work center, workcenter, WC, resource, source of supply, , KBA , procurement priority flag , flag , low priority , /sapapo/rrp313 , /sapapo/rrp319 , SCM-APO-MD-SRC , Sources of Supply , SCM-APO-PPS , Production Planning and Detailed Scheduling , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.