SAP Knowledge Base Article - Preview

2470176 - SAP_PP_021 and REEXPLODE_CHANGE_EXPL_DATE - /SAPAPO/DM_SCHEDFAIL005

Symptom

  • You execute SAP_PP_021 in a Planning Run (/SAPAPO/CDPSB0) and modify the Explosion Date with BAdI /SAPAPO/RRP_EXPLODE, Method REEXPLODE_CHANGE_EXPL_DATE

  • The new Explosion Date is months into the future

  • At the end of the Planning Run, you notice the planned orders were not reexploded and message below was raised:
    • Message no. /SAPAPO/DM_SCHEDFAIL005 - Validity of activity ||| lies outside planning period


Read more...

Environment

  • SAP Supply Chain Management Production Planning and Detailed Scheduling (SCM-APO-PPS)

Product

SAP ERP, add-on for embedded production planning and detailed scheduling all versions ; SAP S/4HANA 1610 ; SAP S/4HANA 1709 ; SAP S/4HANA 1809 ; SAP Supply Chain Management all versions ; SAP enhancement package for SAP Supply Chain Management all versions

Keywords

/SAPAPO/DM_SCHEDFAIL005, /SAPAPO/DM_SCHEDFAIL 005, /SAPAPO/DM_SCHEDFAIL_005, "Validity of activity", "lies outside planning period", ET_SCHED_FAILURES[1]-TYPE 21 , KBA , SCM-APO-PPS-HEU-PP , PP Heuristics , SCM-APO-PPS-SCF , Scheduling Functions , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).