Symptom
Conversion of Planned Order to Production Order does not finish or in incomplete. This has various symptoms:
- Conversion indicator is set for Planned Order in APO/PPDS. The Planned Order is converted in ECC/S4 system to Production/Process order.
- In APO, the order category changes to Production Order, but it still has the Planned Order number. Key completion seems to be is not happening.
- The conversion in APO failed without creating an Error Queue
- Planned Order created in ECC and then converted in ECC are sent to APO without problem and with correct Production Order numbers.
Read more...
Environment
- SAP Supply Chain Management (SCM)
- SAP Advanced Planning and Optimization (SCM-APO)
- SAP enhancement package for SAP Supply Chain Management
- SAP Supply Chain Managment Production Planning and Detailed Scheduling (SCM-APO-PPS)
- SAP Supply Chain Managment Interfaces (SCM-APO-INT)
- S4HANA embedded PPDS
Product
SAP S/4HANA 1610 ; SAP S/4HANA 1709 ; SAP S/4HANA 1809 ; SAP S/4HANA 1909 ; SAP S/4HANA 2020 ; SAP S/4HANA 2021 ; SAP S/4HANA 2022 ; SAP S/4HANA 2023 ; SAP enhancement package 3 for SAP Supply Chain Management 7.0 ; SAP enhancement package 4 for SAP Supply Chain Management 7.0
Keywords
planned order, production order, wrong number, wrong order type, not converted, key completion, /SAPAPO/ORDMAP , KBA , SCM-APO-INT-PPS , PP-DS / Production and Process Order , SCM-APO-PPS , Production Planning and Detailed Scheduling , BC-DB-LCA , liveCache Applications , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.