What happens to the connector jobs, APM jobs which are schduled during the scheduled downtime. ?
What is the process during the release for all the scheduled jobs and APM's?
Environment
SAP SF learning Management System
Resolution
If any connectors or APM are scheduled during the downtime they will not run till the downtime is there but they will resume after the uptime.
That means - if the downtime was 8 am to 10 am then there will be no jobs running at that time (even if they are scheduled to be run), if a job was to run at 9 am then it will not run at 9 am but it will run at 10 am which is when the system is up.