Symptom

When trying to perform Post Goods Receipt or Post Goods Issue against required Inbound Delivery Notification or Delivery Pospal, system crashes.

Environment

 SAP Business ByDesign

Reproducing the Issue

When proforming Post Goods Receipt:

  1. Go to Inbound Logistics Workcenter.
  2. Go to Inbound Delivery NOtifiactions View
  3. Find and select required Inbound Delivery Notification ID.
  4. Select and choose Post Goods Receipt option.
  5. System takes time and crashes.

When proforming Post Goods Issue:

  1. Go to Outbound Logistics Workcenter.
  2. Go to Delivery Proposal View
  3. Find and select required Delivery Proposal ID.
  4. Select and choose Post Goods Issue option.
  5. System takes time and crashes.

Cause

Document contains huge number of line items while performing post goods reciept or post goods issue and hence system takes lot of time processing such a large data and may lead to time out errors. It is a known issue.

Resolution

In order to process such transactions, please follow given steps.

When proforming Post Goods Receipt:

  1. Go to Inbound Logistics Workcenter.
  2. Go to Inbound Delivery Notifiactions View
  3. Find and select required Inbound Delivery Notification ID.
  4. Choose Create Warehouse Request and process the line items using the Site Logistics Task.

When proforming Post Goods Issue:

  1. Go to Outbound Logistics Workcenter.
  2. Go to Delivery Proposal View
  3. Find and select required Delivery Proposal ID.
  4. Choose Create Warehouse Request and process the line items using the Site Logistics Task.