SAP Knowledge Base Article - Public

2491426 - Production Confirmation Missing on Confirmation Journal Report

Symptom

You are using the report Confirmation Journal and the production confirmation ABC for production order XXX is missing in the report.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Business Analytics work center
  2. Select Design Reports view
  3. Search for Confirmation Journal
  4. Open the Confirmation Journal report
  5. Fill the Reference Document ID as XXX
  6. Select Go

See the Production Confirmation ABC is missing

Cause

The report Confirmation Journal only displays documents which have any impact on inventory. If the Production Confirmation ABC has only scrapped quantity, it does not appear on this report.

Resolution

In this case, the system is working as expected. As a workaround, you can:

  1. Fill the Confirmed Quantity with a negative quantity in the Production Confirmation. Doing this, there will be an inventory impact and the Confirmation will appear on report Confirmation Journal. (The prerequisite to confirm negative quantity for input product or output product is, its total confirmed quantity is positive.)
  2. Use the report Yield And Scrap. It will show the Scrapped Quantity on confirmation ABC.

See Also

KBA:  2821131 - You Face an Error When Entering a Negative Quantity in Production Task

Keywords

Confirmation Journal, Production Confirmation, Scrapped Quantity , KBA , AP-LEC , Logistics Execution Control , How To

Product

SAP Business ByDesign all versions