Symptom
- You use Quota Arrangements in PP/DS and the planned material has a Fixed Lot-Size.
- Upon executing the Product Heuristic (SAP_PP_Q001), you notice the Available Quantity is unexpectedly high at a particular day, and that one/some of the receipts could have been scheduled to cover a later requirement
Read more...
Environment
- SAP Supply Chain Managment Production Planning and Detailed Scheduling (SCM-APO-PPS)
Product
SAP ERP, add-on for embedded production planning and detailed scheduling all versions ; SAP S/4HANA 1610 ; SAP S/4HANA 1709 ; SAP S/4HANA 1809 ; SAP Supply Chain Management all versions ; SAP enhancement package for SAP Supply Chain Management all versions
Keywords
SAP_PP_Q001, /SAPAPO/QTA_PEGID_GET_IO, /SAPAPO/QTA_PEGID_DIST_IO, Req. Split, Reqmt splitting, QTSPLT, /SAPAPO/SCC_TQ1, Split Qty, QTSPQTY, Overstock , KBA , SCM-APO-PPS-HEU-PP , PP Heuristics , SCM-APO-CPR-QUO , Quota Arrangement , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results