Symptom

  1. Symptom: Incorrect scheduling dates are returned by ATP check. The calendars maintained for shipping plant and ship-to party are not considered. Checking the explanation screen shows missing LOCTO and LOCFR:

missing LOCTO.jpg

  1. Symptom: The goods receiving hours from the ship-to party master data in ECC system are not correctly considered (e.g. public holidays or weekends will be used for the scheduling).


Read more...

Environment

  • APO - Advanced Planner and Optimizer
  • SAP Supply Chain Management
  • SAP enhancement package for SAP Supply Chain Management

Product

SAP Supply Chain Management 2005 ; SAP Supply Chain Management 2007 ; SAP Supply Chain Management 4.0 ; SAP Supply Chain Management 4.1 ; SAP Supply Chain Management 7.0 ; SAP enhancement package 1 for SAP Supply Chain Management 7.0 ; SAP enhancement package 2 for SAP Supply Chain Management 7.0 ; SAP enhancement package 3 for SAP Supply Chain Management 7.0 ; SAP enhancement package 4 for SAP Supply Chain Management 7.0

Keywords

SCM, timestream, TSTR_INVALIDATE;  enqueue_not_possible, Terminierung, falsch , KBA , SCM-APO-ATP-SCH , Time and Scheduling Functions , Problem

About this page