Symptom
- Is it possible to have Work Schedule Day Model spanning across 2 dates over midnight?
- Save Work Schedule Day Model error: One of the end times is the same as, or earlier than, the corresponding start time. Please correct this.
Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.
Environment
SAP Successfactors Employee Central - Time off and Time sheet
Reproducing the Issue
When we try to create a Work Schedule Day Model which crosses midnight, say the work starts at 9PM and ends at 5AM next morning, we get below error "One of the end times is the same as, or earlier than, the corresponding start time. Please correct this." as the system considers the PM and AM to be from same day:
Resolution
- Cross midnight work schedule is currently not available. We have an enhancement for this functionality but it is not yet confirmed when this will be implemented.
- Enhancement Ticket Number : TIM-6153
- Please follow this KBA for further updates.
Keywords
work schedule day model, work schedule crossing midnight, work schedule spanning midnight, Time off, One of the end times is the same as, or earlier than, the corresponding start time. Please correct this., AM, PM, TIM-6153 , KBA , LOD-SF-EC-TMS , Time Sheet , LOD-SF-EC , Employee Central , LOD-SF-EC-TIM , Time Off , Product Enhancement