Symptom
- When you run MRP heuristic (SAP_MRP_001 or SAP_MRP_002) other products, beyond those specified, are planned too
- MRP is planning products that do not meet the selection of products for the processing step
- You are seing different results in Product View (Tcode /SAPAPO/RRP3) when running Product Heuristic, compared to the execution of MRP Heuristic at Planning Run (Tcode /SAPAPO/CDPSB0) for the same product @ location
Read more...
Environment
- SAP Supply Chain Management Production Planning and Detailed Scheduling (SCM-APO-PPS)
Product
SAP S/4HANA all versions ; SAP Supply Chain Management all versions ; SAP enhancement package for SAP Supply Chain Management all versions
Keywords
/SAPAPO/HEU_MRP_PLANNING , KBA , SCM-APO-PPS , Production Planning and Detailed Scheduling , How To