SAP Knowledge Base Article - Public

2531548 - How the Learning Plan periods are calculated

Symptom

How is the period for classification of the categories in the Learning Plan calculated?

Environment

SuccessFactors Learning Management System (LMS)

Resolution

The current day is counted as the first one of the current period and the last day of a period (ex. 7 for a week) is the last date for a course to be shown inside that category.

For example, if the course is due in June 13th, it will show in "Due Later" until July 12th, when it will change to the "Due Within a Month" section. Further on, in June 19th it will change to "Due Whitin a Week".

Keywords

Due Within, Learning Plan, Period, To Do, List, Course, Item, Required, Assignment, Date , KBA , LOD-SF-LMS-COR , LMS Core - Items, Catalog, Curricula , How To

Product

SAP SuccessFactors Learning all versions