2532992 - Error While Migrating Projects With Status Completed

Symptom

You find below options in the text help for the Migration of Projects template in the Project Status field description:

Project Status*

An identifier that defines the stage a project has reached. Enter one of the following numbers to define the status: 
'1' (for planned) '2' (for started) '3' (for released) '6' (for completed)

However, you receive below error when you use status code value as 4.

"Error detected in source record with key value 'PRXXX' Goto Correction;
Action FINISH not possible; action is disabled"

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Business configuration work center
  2. Select Overview view
  3. Search Migration of Projects activity
  4. Select Migrate Projects using Migration Tool
  5. Execute Migration step by step

Cause

It is only possible to Migrate Projects which are not yet finished. It means Projects which are in status 1, 2 or 3 can be migrated using the Migration of Projects Activity.

Resolution

Currently in help text for the Project Status field shows more values than we really support in the migration template. This is a mismatch to the values we really use in projects from User Interface:

  1.  In Planning
  2.  Started
  3.  Release
  4.  Stopped
  5.  Closed
  6.  Completed

Use the options 1(Planned), 2(Started), 3(Released) in the Migration Template and re-execute. We shall rectify the help text in the template in one of the future releases.

See Also

KBA 3416500 - Error: "Start date must not overlap with another planned period" during Project Migration

Keywords

Projects; Migration , KBA , migration of projects , SRD-CC-MIG-DMC , Migration: Tool , How To