Symptom
The calculated fields(Date related calculation) in integration centre show correct calculations in the UI and in Calculation Trace, but when file output is created ALL output records have the same value regardless of calculation used.
Environment
Integration Center
Reproducing the Issue
To reproduce the issue use data related calculation in the IC
For Example:
Cause
Here the date format is causing the issue.
Resolution
We should use the following format YYYY-MM-ddTHH:mm:ssZ
For Example:
Keywords
- Date calculation does not work
- Output of integration center does not have correct values
Product
SAP SuccessFactors HCM Core 1702