Symptom
After performing Integration and Planning for a Portfolio Item, the costs from Project System are transferred successfully to Portfolio Management (as seen in table RPM_FIDATA), however the item's financial planning table is empty.
Read more...
Environment
- SAP Portfolio and Project Management
- SAP Portfolio and Project Management for SAP S/4HANA
- SAP S/4HANA
- SAP S/4HANA Cloud Private Edition
Product
Keywords
/RPM/PLANNING011, /RPM/PLANNING012, /RPM/PLANNING 011, /RPM/PLANNING 012, "Start date missing for item ...; cannot plan for period type TOTAL", "Finish date missing for item ...; cannot plan for period type TOTAL", empty, zero, actual costs, planned costs , KBA , PPM-PFM , Portfolio Management , Problem