Symptom
To prevent planned orders from scheduling by MRP, planned orders are firmed as below but that is still scheduled when planning mode '2' is used.
Read more...
Environment
- Production Planning (PP)
- SAP R/3
- SAP R/3 Enterprise 4.7
- SAP ERP Central Component
- SAP ERP
- SAP enhancement package for SAP ERP
- SAP enhancement package for SAP ERP, version for SAP HANA
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
Fixed, MD11, Basice scheduling. , KBA , PP-MRP-PP , Procurement Proposal , How To