Symptom
-
UJBR backup takes longer than before. For example, original it was taking 6 hours to finish the backup, but it is taking more than 24 hours to complete the backup.
-
The transaction is not dramatically increased and the backup options are the same.
-
The lite optimize has been executed but the backup time is not improved.
- ST12 trace shows that the majority of the time occurs in retrieving data from with table starting with $BPC$TMP. You tried to run program UJHANA_DELETE_BPC_TMP_TABLE(see Note 2445363) to clean the temp tables, but situation is not improved.
Read more...
Environment
- SAP BusinessObjects Planning and Consolidation 10.0, version for SAP NetWeaver
- SAP BusinessObjects Planning and Consolidation 10.1, version for SAP NetWeaver
Product
SAP Business Planning and Consolidation 10.0, version for SAP NetWeaver ; SAP Business Planning and Consolidation 10.1, version for SAP NetWeaver
Keywords
KBA , EPM-BPC-NW-BR , Backup & Restore , Problem