Symptom
You are trying to release customer demand document created against a Project Stock Order. However, system displays the below error message.
The source of supply cannot be determined; check the sourcing-relevant master data.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Outbound Logistics Control work center.
- Navigate to the Customer Demand view.
- Search for the relevant document, select it and choose Check Availability
The below error message is displayed
The source of supply cannot be determined; check the sourcing-relevant master data.
Cause
We could see Project Stock Order is created and the ATP is not confirmed since there is no stock available
Resolution
Once we have stock in Logistics area we will be able to perform the Check Availability and release Customer Demand.
Keywords
The source of supply cannot be determined; check the sourcing-relevant master data, While Trying to Release Customer Demand Document Created Against a Project Stock Order , KBA , project stock order , the source of supply cannot be determine , AP-CR-CR , Customer Requirement , Problem