Symptom

The calculation of the field Requested Delivery Date does not exclude non-working days.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to the Sales work centre.
  2. Go to the Sales Order view.
  3. Select a Sales Order ABC (ABC represents the Sales Order ID).
  4. For the field Creation Date a date XYZ is maintained (XYZ represents the date).
  5. For the field Requested Delivery Date, the date XYZ + amount of day(s) is automatically filled.

The returned date for the field Requested Delivery Date falls on a non-working day.

Resolution

This is expected system behaviour.

Keywords

Requested Delivery Date, Sales Order, Working Day, Request, Calendar, Non, Calculation, Requested Date, Delivery Date, Wrong , KBA , AP-SLO-SO , Sales Order , Problem