Symptom
How to make a non-working day (e.g Saturday) as a working day in Time Off?
Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.
Environment
- SAP SuccessFactors Employee Central
- SAP SuccessFactors HXM Suite
Reproducing the Issue
- As per Work Schedule, employees work 5 days a week. (e.g Monday - Friday; Saturday and Sunday are non-working days);
- The requirement is to set one non-working day (say 2nd Dec 2017 (Saturday)) as a working day.
Cause
Resolution
This can be achieved using Temporary Time Information.
- Create a Work Schedule with only one day, which is a working day. (e.g 2nd Dec 2017 as Working day. Rest of the days configure it as non-working days);
- Create a Temporary Time Information for all users who should be working and assign it to this created Work Schedule. You can do this via MDF Import in a Mass scenario.
NOTE: If this is only a non-working day via Holiday Calendar, you have to remove the holiday from the Holiday Calendar and create a Recalculation event as well.
See Also
2328948 - Time Off: How to recalculate leave balances when Holiday Calendar is updated - SAP for Me
2277994 - How to Import Data for MDF Objects/MDF picklists in SuccessFactors? - SAP for Me
Creating a Temporary Work Schedule | SAP Help Portal
Keywords
Time off, Temporary Time Information, Non Working day, Saturday, Sunday, Working Day, Holiday, how to , KBA , LOD-SF-EC-TIM-JOB , Time Management in Job Info - Records & Objects , LOD-SF-EC-TIM , Time Off , How To