Symptom
In the Project Planning Board you move a network activity. Only the Earliest set of dates are updated. (This KBA also applies to Latest dates).
Read more...
Environment
- SAP ERP Project System (PS)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
- SAP S/4HANA, cloud edition
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
TCBP-UPDTS, scheduling carried out, CO250, CO 250, LCJGRF34 FORM MOVE_OBJ_HORIZONTALLY, Earliest Start Date, AFVGD-FSAVD, Earliest Finish Date, AFVGD-FSEDD, Latest Start Date, AFVGD-SSAVD, Latest Finish Date, AFVGD-SSEDD, bc_node_vals, LCJGRF0O, CJGR_CALLBACK_BARC1_PAI, BARC_GRAPHIC_PAI, node_vals , KBA , PS-ST-PPB , Project Planning Board , How To