SAP Knowledge Base Article - Public

2580565 - While Creating a New Planning Proposal for a Product and Planning area, Error Appears

Symptom

Multiple Errors when creating  new planning proposal for product KLM.*KLM  refers to Product id*DEF represents Planning area id,  *XX.YY.ZZZZ refers to Date

Proposal could not be created; check availability date.
Creation of all receipts not possible.
Transportation lane for KLM DEF on XX.YY.ZZZZ for quantity XY  not found.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Supply Planning Work Center.
  2. In Common tasks click New Planning Proposal.
  3. Enter Product KLM,Planning area DEF and quantity xy (xy represents quantity in no's) etc

Error appears

Proposal could not be created; check availability date.
Creation of all receipts not possible.
Transportation lane for ABC DEF on XX.YY.ZZZZ for quantity XY  not found.

Cause

Although the setting maintained for Product Master ABC Planning area DEF, Procurement type is internal procurement (stock transfer) in planning screen of product master data.

The transportation lane maintained  has only ship from site.

Resolution

In case of stock transfer scenario, ship to location need to be maintained in transportation Lane.

BoM / BoO / Production Model comes into picture if the setting maintained as: In-house production for procurement type in planning tab of Product Master data.

Keywords

Proposal could not be created; check availability date, Transportation lane for quantity  not found , KBA , creation of all receipts not possible , proposal could not be created; , transportation lane for not found , product in planning area , AP-SDM , Supply and Demand Matching , Problem

Product

SAP Business ByDesign all versions