Symptom
If the requirement quantity or date or BOM is changed, then you run t-code MD01N with planning mode 1, the existing procurement proposals such as purchase requisitions or planned orders are deleted and recreated. But if t-code MD03 is used in this case, the existing procurement proposals are adjusted with new quantity or date.
Read more...
Environment
- SAP ERP Production Planning (PP)
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
Product
Keywords
MD01, MD02, MD03, reuse, planned order, procurement proposal, change date, change quantity, adapt planning data, delete and recreate planning data, BOM change , KBA , PP-MRP , Material Requirements Planning , Problem