SAP Knowledge Base Article - Public

2590650 - Purchase Proposals Does not Show Earliest Requirement Dates

Symptom

Earliest Requirement Date is missing in Purchase Proposal KLM*KLM refers to Purchase Proposal Id

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Supply Control work center
  2. Navigate to Process Purchase Proposal view
  3. Select All proposals by selection
  4. Search for Purchase Proposal KLM
  5. Navigate to sub tab Proposal Details

You observe purchase proposal KLM earliest requirement date is missing for Material ID DEF.*DEF refers to Material Id

Cause

Purchase Proposal KLM is a firm proposal which means it is manually created. Firm Proposals will not have Earliest Requirement date.
Earliest Requirement is something related to proposals that are created by MRP run because of some demand, Demand may be like Sales
Order, Stock Transfer Order etc.

Resolution

Firm Proposals will not have Earliest Requirement date.
Earliest Requirement is something related to proposals that are created by MRP run because of some demand, Demand may be like Sales
Order, Stock Transfer Order etc.This is the standard system behaviour.

Keywords

Earliest Requirement Date is missing, Purchase Proposal does not contain Earliest Requirement Date. , KBA , earliest requirement date is missing , purchase proposal does not contain erd , AP-SDM-PCO , Procurement Planning Order , Problem

Product

SAP Business ByDesign all versions