Symptom
Earliest Requirement Date is missing in Purchase Proposal KLM*KLM refers to Purchase Proposal Id
Environment
SAP Business ByDesign
Reproducing the Issue
-
Go to Supply Control work center
- Navigate to Process Purchase Proposal view
- Select All proposals by selection
- Search for Purchase Proposal KLM
- Navigate to sub tab Proposal Details
You observe purchase proposal KLM earliest requirement date is missing for Material ID DEF.*DEF refers to Material Id
Cause
Purchase Proposal KLM is a firm proposal which means it is manually created. Firm Proposals will not have Earliest Requirement date.
Earliest Requirement is something related to proposals that are created by MRP run because of some demand, Demand may be like Sales
Order, Stock Transfer Order etc.
Resolution
Firm Proposals will not have Earliest Requirement date.
Earliest Requirement is something related to proposals that are created by MRP run because of some demand, Demand may be like Sales
Order, Stock Transfer Order etc.This is the standard system behaviour.