SAP Knowledge Base Article - Public

2591441 - Reschedule Bottom-Up Action in Resources Does not Affect Production Proposal Dates

Symptom

You are performing Reschedule Bottom-Up action on a production resource. You see that the Start Date of the proposals does not get rescheduled as you expect.

Reproducing the Issue

1.Go to the Supply Planning work center.

2.Navigate to the Resource Load view.

3.Search for the relevant resource and choose the Open button.

4.In the Resource Planning Details screen, choose the Reschedule Bottom-Up button.

 

When you check your production proposals using the above resource you see that the Start Date of the proposals are not rescheduled.

Cause

Performing the Reschedule action on the resource will not change the Start Date of the proposals of a particular product. You have to perform the Reschedule Bottom-Up action for a product from the material Flow view of the product available in the lowest level of the production chain. This will make sure that all the proposals in the above top level are adjusted accordingly.

Resolution

1.Go to the Supply Planning work center.

2.Navigate to the Products view.

3.Search for the relevant product whose proposals you need to reschedule, select it and choose the button Open.

4.In the Product Planning Details screen, select the production proposal and choose the button Open Material Flow.

5.In the Material Flow screen you can perform the Reschedule Bottom-Up action for the product available in the lowest level of the production chain.

 

Performing the above steps will adjust all the proposals in the above level accordingly.

Keywords

Supply Planning, Production Proposal, Reschedule, Bottom-up, Resources, Product , KBA , AP-SDM-SPR , Supply Planning Requirement , Problem

Product

SAP Business ByDesign all versions