2597566 - On-Hand Stock in Project Material Flow is Zero

Symptom

On hand stock in project material flow is zero while it shows non-zero value in stock overview.

Environment

SAP Business Bydesign All versions

Reproducing the Issue

  1. Go the Internal Logistics work center.
  2. Go to the Stock Overview view.
  3. Enter Material ID XYZ (XYZ stands for material ID).
  4. Enter Logisitcs area ABC (ABC stands for Logistics area ID).
  5. Enter Identified Stock XXX (XXX stands for Identified Stock ID).
  6. Click Go.
  7. You can see that on-hand stock is YYY (e.g 20 ea).
  8. Go to Internal Logistics work center.
  9. Go to Project Material Flow view.
  10. Enter the same paramenters.
  11. Click Go.
  12. You can see that on-hand stock is 0 ea.

Cause

Identified Stock XXX has already expired. Project Material Flow considered stock of expired identified stock as zero on-hand stock.

Resolution

  1. Go to Planning and Production Master Data Work center.
  2. Go to Identified Stock View
  3. Search Identified Stock XXX
  4. Select it and Click Edit.
  5. Change the expiration date to a future date.
  6. Click Save and Close.

Keywords

Zero on-hand stock; Project Material Flow , KBA , AP-SLP , Site Logistics Processing , How To