Symptom
On hand stock in project material flow is zero while it shows non-zero value in stock overview.
Environment
SAP Business Bydesign All versions
Reproducing the Issue
- Go the Internal Logistics work center.
- Go to the Stock Overview view.
- Enter Material ID XYZ (XYZ stands for material ID).
- Enter Logisitcs area ABC (ABC stands for Logistics area ID).
- Enter Identified Stock XXX (XXX stands for Identified Stock ID).
- Click Go.
- You can see that on-hand stock is YYY (e.g 20 ea).
- Go to Internal Logistics work center.
- Go to Project Material Flow view.
- Enter the same paramenters.
- Click Go.
- You can see that on-hand stock is 0 ea.
Cause
Identified Stock XXX has already expired. Project Material Flow considered stock of expired identified stock as zero on-hand stock.
Resolution
- Go to Planning and Production Master Data Work center.
- Go to Identified Stock View
- Search Identified Stock XXX
- Select it and Click Edit.
- Change the expiration date to a future date.
- Click Save and Close.
Keywords
Zero on-hand stock; Project Material Flow , KBA , AP-SLP , Site Logistics Processing , How To
Product
SAP Business ByDesign all versions
SAP Knowledge Base Article - Public