Symptom
There are several valid external source of supplies for a material. This KBA explains which one should be selected when running MRP in S/4 HANA system.
Variant 1.:
for releases before (or without SAP Notes 3233269 classic MRP or 3208310 MRP live):
107 SP02
106 SP04
105 SP06
104 SP08
103 SP10
102 SP12
See solution text for Variant 1.
Variant 2.:
With SAP Note 3233269 (MRP classic) or 3208310 (MRP Live) implemented or having one of the releases:
107 SP02
106 SP04
105 SP06
104 SP08
103 SP10
102 SP12
Or later
See solution text for Variant 2 .
Read more...
Environment
- SAP S/4HANA, on-premise
- SAP S/4HANA Cloud Private Edition
Product
Keywords
priorization, sourcing, MRP, schedule line, CDS_M_PUR_SOS_B, EKET, EINA, EINE, MD01n, MD02, MD03, MD01, MRP Live, vendor , KBA , PP-MRP-PP , Procurement Proposal , MM-CBP-CBP , Consumption-Based Planning (see also PP-MRP) , How To