Symptom
How to update the connector schedule?
Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.
Environment
SAP SuccessFactors Learning
Cause
The business requires a connector to run in a different scheduled.
Resolution
In the Learning admin side, click:
-
System Administration > Connectors > Select the desired connector to have its schedule adjusted >
-
In the "Schedule" area, set it as desired > Apply Changes.
See the "Note" section near the bottom. It will specify what the timezone the date/time values should be in as per the KBA 2626409 - Specifying date/time fields in Connector input files - Timezone.
See Also
Keywords
connector, change, schedule, update, time, hourly, daily, weekly, monthly, run, how to, restart, job , KBA , LOD-SF-LMS , Learning Management System , LOD-SF-LMS-CON , Connectors , Problem