The business requires a connector to run in a different scheduled.

Resolution

In the Learning admin side, click:

  1. System Administration > Connectors > Select the desired connector to have its schedule adjusted >
  2. In the "Schedule" area, set it as desired > Apply Changes.

See the "Note" section near the bottom. It will specify what the timezone the date/time values should be in as per the KBA 2626409 - Specifying date/time fields in Connector input files - Timezone.

See Also

2409791 - Unable to schedule Connector job in LMS system as Schedule This Process checkbox is greyed out

2626409 - Specifying date/time fields in Connector input files - Timezone

Keywords

connector, change, schedule, update, time, hourly, daily, weekly, monthly, run, how to, restart, job , KBA , LOD-SF-LMS , Learning Management System , LOD-SF-LMS-CON , Connectors , Problem

Product

SAP SuccessFactors Learning all versions