SAP Knowledge Base Article - Public

2624698 - Production Task Was assigned to a Wrong Task Folder

Symptom

Production Task was assigned to a Wrong Task Folder.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to the Production Control work center.
  2. Go to Task Control view.
  3. Show all and search for Task ABC (ABC means the Task ID).
  4. The task ABC is in Task Folder XYZ (XYZ means Task Folder ID), however it should be assigned to Task Folder OPQ (OPQ means Task Folder).

Cause

It can be checked the Bill of Operations details in the corresponding Production Model, the Task - Generation Method is maintained as "Operation including Report Points". However, for Production Task folder OPQ, the type is maintained as "Activity". This means that only tasks that are generated per activity can be dispatched to the folder OPQ. But here tasks are created based on operations.

Resolution

In order to use task folder OPQ for production tasks, it is necessary to either remove the activity type values in the Assignment Criteria of the production task folders or change the Task-Generation Method in the bill of operation.

Keywords

Production Task Folder, Task Control,  Bill of Operations , KBA , AP-PE , Production , How To

Product

SAP Business ByDesign all versions