Symptom
Error Message: Product XYZ in Planning Area ABC Planned with Failures; While Running Material Requirement Planning(MRP)
Environment
SAP Business Bydesign All versions
Reproducing the Issue
- Go to the Supply Planning work center.
-
Select the Products view.
-
Select All Products By Selection from Show drop down and select Advanced link.
-
Enter XYZ in the Product ID field and ABC in the Planning Area ID field.
-
Choose Go button.
-
Select the searched product and select Open button.
-
In the Product Planning Details screen, select either Single BoM Level or Multi BoM Level from Run Planning drop down. System shows error message: Product XYZ in Planning Area ABC Planned with Failures.
Cause
The valid from date of production model for product XYZ is later than the execution date on date. e.g. Execution Start Date is March 23rd 2018, but production model is valid from Mar 24th 2018.
Resolution
- Go to Planning and Production Master Data.
-
Go to Production Models view.
-
Search the production model for product XYZ.
-
Click Edit.
-
Change the valid from date to the date earlier than execution start date.
-
Click Release Production Model for planning and execution.
-
Click Save.
Keywords
MRP, Production Models , KBA , AP-PMM , Production Model Management , How To
Product
SAP Business ByDesign all versions