SAP Knowledge Base Article - Public

2624793 - Error message:Resource used by REPM production segment

Symptom

Error message:Resource used by REPM production segment triggers when you try to remove a resouce from a logistics area.

Environment

SAP Business Bydesign All versions

Reproducing the Issue

  1. Go to Supply Chain Design Master Data
  2. Go to Location view
  3. Select Site ID XYZ
  4. Click Edit Layout
  5. Select Logistics Area ABC
  6. Navigate to Resources Tab
  7. Select Resource ZZZ.
  8. Click Remove
  9. Error message:Resource used by REPM production segment

Cause

Once the resouce ZZZ was used in any versions of a released execution production model (REPM), it cannot be removed.

Resolution

As a workaround, you can block the resource or set it as obsolete.

Keywords

Resource, REPM , KBA , AP-PMM , Production Model Management , How To

Product

SAP Business ByDesign all versions