Symptom

  • You have created a contract as follow-up for a Quote for Contract, which set the Quote for Contract in status "Completed".
  • Upon cancellation of the Follow-Up Contract, the Quote for Contract reopens.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Create Quote for Contract ABC (ABC represents the ID of the Quote for Contract).
  2. Create a Follow-Up Contract DEF (DEF represents the ID of the Contract) from Quote ABC and release it.
  3. Navigate to the Sales Quote View in the New Business work center.
  4. When you find Quote ABC, it will be in status Completed.
  5. Open Contract DEF.
  6. Navigate to the Items Tab.
  7. Select any Line Item and select a Reason for Rejection.
  8. Wait until the created Cancellation Task is processed and the Line Item is in Status Completed in the Contract.
  9. Navigate to the Sales Quote View in the New Business work center.
  10. When you find Quote ABC, it will be in status In Process/Open.

Cause

  • Quotes for Contract only remain in status Completed if the line items from the quote in the follow-up contract are completed.
  • If one Line Item is cancelled, the Quote for Contract will be open again.
  • If a Line Item is removed, the Quote for Contract will be open again.

This is the expected system behaviour.

Resolution

  1. In order to avoid opening quotes, the line items in the follow-up contract cannot be cancelled.
  2. The line items need to be completed by automatically created Business Tasks, that are triggered, when a contract is created.
  3. Find more information which conditions needs to be fulfilled in Knowledge Base Article 1945450.

This behaviour applies also for service and sales quotes, where in the follow up order line items are cancelled.

See Also

Knowledge Base Article 1945450 - The Contract Status is not Completed, Even After the Items are Fulfilled and Invoiced, click here.

Keywords

Vertrag, Angebot, Offen, Abgeschlossen, Stornieren, Absagegrund, Contract, Quote, Open, In Process, Completed, Cancel, Reason for Rejection, Sales Order, Service Order , KBA , AP-CCP , Customer Contract Processing , AP-CQP , Customer Quote Processing , Problem

Product

SAP Business ByDesign 1802