2627356 - Resource demand is not deleted when cancelling a project or task

Symptom

A resource has been staffed to a project role and assigned to a task. You cancel the task, or cancel the whole project. You notice that the planned effort / demand of the resource is not deleted or truncated.


Read more...

Environment

  • SAP cProject Suite (PPM-PRO)
  • SAP Portfolio and Project Management (PPM)
  • SAP Portfolio and Project Management for SAP S/4HANA (PPM)
  • SAP Portfolio and Project Management in SAP S/4HANA (PPM)

Product

SAP Portfolio and Project Management all versions ; SAP Portfolio and Project Management for SAP S/4HANA all versions ; SAP S/4HANA all versions ; SAP cProject Suite 4.5

Keywords

cancel, canceling, status, truncate, work effort, resource effort, assigned effort , KBA , PPM-PRO , Project Management , Problem