Symptom
When you try to Confirm Production Task 9999 with Input Products and select Split, system does not Split the Input Products.
Environment
SAP Business ByDesign
Reproducing the Issue
1. Go to Production Control workcenter and Task Control view
2. Find Task 9999 and Confirm
3. Go to Confirmation Tab and Input Products sub tab
4. Select any product Productxyz and click on Split
We do not see the split of Input Product.
Cause
This happens because of the current hierarchical design between confirmation group, activity and material input maintained in Production lot and its linkage with production task.
Resolution
The solution for this is not straight forward.
As a work around we suggest whenever you use Task Creation Strategy in Bill Of Operations as Operations Including Reporting Point or Activities Including Reporting Point, you should give Reporting Point after every operation in the Production Model.
Once this is done Split will work as expected.
Keywords
Production Task, Input Products, Split, Task Creation Strategy, Reporting Point , KBA , production task , split , task creation strategy , reporting point , input products , AP-PE-TSK , Production Task , Problem