Symptom
Target Logistics area is unchangeable for replenish task created with reference of Production Order.
Environment
SAP Business Bydesign All Versions
Reproducing the Issue
- Go to Internal Logistics Work Center.
- Go to Task Control View.
- Search task XXX (XXX stands for replenish task ID) and click confirm.
You can see the target logistics area is ABC (ABC stands for logistics area ID), and it is not changeable.
Cause
For replenish task created with reference of Production Order, the target logistics area is fetched from Production Order. Open Production Order, Click View all , Navigate to Products tab , select Input product tab, here you can see the logistics area for input products.
You have requested replenishment for logistics area ABC , which means this logistics area needs to be replenished. That is why system created replenishment task with target logistics area as ABC. Since replenishment is requested for Logistics Area ABC, so system does not allow to change the logistics area.
Resolution
Customer could the change the logistics area before release the production order. Once it is released, it could not be changed.
Keywords
Target Logistics Area, Replenish Task, Production Order , KBA , AP-SLP , Site Logistics Processing , How To