Your requirement is to migrate Bills of Operations, but you receive the below error in the Simulation step:
Resource XYZ has status In Preparation and must not be used
Resource PQR must be relevant for scheduling
*XYZ and PQR represents the Resource
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Business Configuration work center
- Select Implementation Projects view or Overview
- Search and Open the activity Migration of Bills of Operations
- Select Migrate bills of operations using the migration tool
- Upload the Migration File
- Execute Migration for the respective Migration File with Migration Mode Add new records
- You receive the error message mentioned in the Simulation step
Cause
In the work center Supply Chain Design Master Data, the Status of the Resource is In Preparation. Further, the Resource has not been relevant for scheduling.
Resolution
Change the Status of the Resource to Active and make them Relevant to Scheduling before you proceed with the migration.
Keywords
Migration of Bills of Operations, Bills of Operations, Resource has status In Preparation and must not be used, Resource must be relevant for scheduling , KBA , bills of operations , resource has status in preparation and m , resource must be relevant for scheduling , migration of bills of operations , AP-PMM-PBO , Production Bill of Operations , Problem